# Follow and close a sprint

> See the sprint work for you, your teams or one project or team on the Sprints page, then close the sprint and carry unfinished tasks over.

The **Sprints** page shows the work of the current sprints in one table: your own, your teams', or everything in the sprint of one project or team. When a sprint is over, close it there, and the tasks that are not finished move on to the next sprint.

## See your sprint work

Choose **Sprints** in the sidebar. The page opens on **Me**: the tasks and run steps assigned to you in the current sprints of all your projects.

![The Sprints page with your own work in the current sprints](https://okido.io/docs/screenshots/en/sprints-page.webp)

The items are grouped by status. Use the buttons above the table to group them differently or to choose the columns. Click a task to open it. Select **Show all sprints** to see your work in every sprint, not only the current ones.

## Choose whose work you see

1. Choose the button at the top right that shows whose work you see.
2. Choose **Me**, **My Teams**, a team or a project.
   ![Choosing whose sprint work to see](https://okido.io/docs/screenshots/en/sprint-scope-picker.webp)
3. For a team or a project, choose a sprint in the list next to it. The sprint that runs today is chosen for you.

For a team or a project, the bar above the table shows the sprint's dates, its status and how many tasks and run steps it holds. On the right, the meeting notes of the sprint open; see [Run a sprint meeting](https://okido.io/en/docs/planning/run-a-sprint-meeting.md). The button with the panel icon at the top right hides them, to give the table more room.

## Close a sprint

1. Choose the project or team and the sprint.
2. Choose **Close Sprint**.
   ![The Close Sprint button of the current sprint of a project](https://okido.io/docs/screenshots/en/close-sprint.webp)

OKiDO closes the sprint and moves its unfinished tasks to the next sprint of the same project or team: the first active or planned sprint that starts after this one ends. Finished tasks stay in the closed sprint, and a closed sprint can no longer be chosen in a task's **Sprint** field.

Only organization owners and admins can close a sprint.